MARITIME PIER, RAMP & FLOAT PROJECT CONSTRUCTION UPDATE- SEPTEMBER 5, 2012

Anticipated Upcoming Project Schedule

The contractor hired by the City “Redside Construction, LLC” to perform the work is scheduled to be onsite until mid-October.

Work scheduled for the next two weeks:

· Pile driving (piles for float)

· Assembling & placing timbers & lumber

· Delivery & placement of float/gangway

Project Milestones

· Pile driving for pier is complete

Some public parking will be restricted at the site during progress of this work.

The rest of the treated lumber package for construction of the pier is scheduled to arrive at the site this week. The gangway and the float will also be delivered soon. These materials will be delivered by truck, which will briefly disrupt traffic.

Reminder

If you would like to receive project information and construction updates and be included on our stakeholders list, please provide your contact information to Jami Chunn at chunnj@cityofgigharbor.net or (253) 853-7625 and indicate that you wish to be added to the stakeholders list for the Maritime Pier, Ramp & Float Project. Also, please check the City’s website (www.cityofgigharbor.net) for routine project updates and notices.