Olympic Drive Bridge Approach Paving Will Take Place The Night Of May 16th

Olympic Drive Bridge approach paving will take place the night of May 16th .

Work will consist of full lane width grinding down 3- 4 inches in depth ten feet out from the bridge end. Standard spec. Hot Mix Asphalt (HMA) will be laid back in with a grader and compacted with a steel wheel roller.

The public can expect crews to start taking the lane by 9pm and reopening to traffic no later than 5am. WSDOT is planning four nights to compete the work. Programmable message boards will be placed May 9th notifying the public in advance of the upcoming impacts. Lane shifts will be used to move traffic through the work zone.

Please drive with caution through this work area.