April 26 weekend closure of westbound SR 16 Tacoma Narrows Bridge delayed

                

April 26 weekend closure of westbound SR 16 Tacoma Narrows Bridge delayed

 

TACOMA – Drivers who were preparing for the April 26 weekend closure of the westbound State Route 16 Tacoma Narrows Bridge can take a breather.  A project to replace a problematic expansion joint has been delayed a few weeks. 

 

The Washington State Department of Transportation and its contractor, Mowat Construction, learned today, April 12, that the new expansion joint, which is being fabricated specifically for this bridge, will not be ready in time. The work and associated traffic restrictions will more likely occur in mid-May.

 

A new closure date will be announced once WSDOT can verify a new schedule with certainty.  This delay will not affect the overall contract schedule or budget.  

 

Washington State Department of Transportation - NEWS
Olympic Region – PO Box 47440 - Olympia, WA  98504-7440 – 360-357-2600

 

FOR IMMEDIATE RELEASE                                                                                                    

April 12, 2013

 

Contacts:    Claudia Bingham Baker, WSDOT Communications, 360-357-2789 (Tumwater)

 

###

WSDOT keeps people, businesses and the economy moving by operating and improving the state's transportation systems. To learn more about what we're doing, go to www.wsdot.wa.gov/news for pictures, videos, news and blogs. Real time traffic information is available at www.wsdot.wa.gov/traffic or by dialing 511. 