Project Background

This project includes the replacement of undersized and deteriorating asbestos cement water main located in the Harbor Heights residential area (Lewis Street, Shyleen Street, Butler Drive, McDonald Avenue, and Pioneer Way). This project was identified in the City’s 2011 Budget under the Water Division – Capital Fund.

Project Update

A majority of the new water main has been installed in this area. The remaining two hundred feet of water main will be placed in Pioneer Way north of Edwards Drive over the next few days.

Asphalt paving will occur during daylight hours and is scheduled to begin on October 24 and be completed by October 28, depending on weather. The Contractor will use traffic control along Pioneer Way to maintain alternating one-way traffic. When paving on the residential roadways, temporary road closures and/or detours will be utilized.

Thank you for your patience while this project is being completed.