DONKEY CREEK RESTORATION & TRANSPORTATION IMPROVEMENTS PROJECT

April 10, 2013

Upcoming Work: The contractor plans to begin rock placement for the rock walls and complete placement of the base and top courses along Austin Street next week.

Work In Progress: Rock and block wall preparation continues. The contractor is utilizing a single-lane closure along North Harborview Drive between Burnham Drive and Austin Street with a one-way detour up Burnham Drive to ensure that there is sufficient room for the work to be completed safely. Installation of the rock and block wall under-drain pipe is also in progress, along with miscellaneous storm system work along the periphery of Austin Street.

Work Completed: The two water tie-in installations were completed last week as scheduled. Tree removal along Austin Street has also been completed.

ACCESS TO ALL BUSINESSES and RESIDENCES WILL BE MAINTAINED AT ALL TIMES.

Primary project contact:
Jeff Olsen
Construction Supervisor
OlsenJ@cityofgigharbor.net
(253) 255-8233

Emily Appleton, P.E.
Project Manager/Sr. Engineer
AppletonE@cityofgigharbor.net
(253) 853-7620

Project Updates:
Project updates will be posted on the Donkey Creek Restoration website at www.DonkeyCreekRestoration.com.

The City will circulate periodic updates by email. If you know someone that would be interested in receiving these email notices, please contact Project Admin. Assistant Maureen Whitaker at WhitakerM@cityofgigharbor.net.