Back To News

MARITIME PIER, RAMP & FLOAT PROJECT CONSTRUCTION UPDATE- AUGUST 22, 2012

Anticipated Upcoming Project Schedule

The contractor hired by the City, “Redside Construction, LLC” to perform the work is scheduled to be onsite until mid-October.

Work scheduled for the next two weeks:

· Pile driving (fender piles)

· Preparation for placing pile caps

· Construction of float (off-site)

Project Milestones

· The new ramp has been assembled (off-site)

Some public parking will be restricted at the site during progress of this work.

The treated lumber package for construction of the pier is scheduled to arrive at the site early next week. These materials will be delivered by truck, which will briefly disrupt traffic.

Reminder

If you would like to receive project information and construction updates and be included on our stakeholders list, please provide your contact information to Jami Chunn at chunnj@cityofgigharbor.net or (253) 853-7625 and indicate that you wish to be added to the stakeholders list for the 56th Street/Point Fosdick Drive Improvement Project. Also, please check the City’s website (www.cityofgigharbor.net) for routine project updates and notices.

Questions?

If there are any questions please contact Marcos McGraw, Project Engineer at mcgrawm@cityofgigharbor.net or (253) 853-2647.